Firm or tentative: check your Statement of Critical Dates
Every new freehold home agreement in Ontario includes a Tarion Addendum. Its first page, the Statement of Critical Dates, sets every date that matters. Builders choose one of two kinds of closing date (Tarion):
- Firm Closing Date: the builder commits to a date. If it misses it, compensation starts.
- Tentative Closing Date: used when construction has not started or timing is uncertain. The builder can push the date twice, by up to 120 days each time, without paying you anything.
Most pre-construction homes start with a tentative date, so a "fall 2028" closing can legally become mid-2029 with no compensation if the builder gives proper notice.
How tentative dates can move
With a tentative date, the builder must give you written notice at least 90 days before the First Tentative Closing Date to extend it. If it does not, that date automatically becomes your Firm Closing Date. The same 90-day rule applies to the second extension.
The latest Firm Closing Date is the First Tentative Closing Date plus 240 days. After that, the Outside Closing Date is 365 days later. That is the last date the builder can close without you having the right to cancel (Tarion).
What compensation you are owed
Once a Firm Closing Date is missed, the builder must set a Delayed Closing Date and you are entitled to compensation, up to a maximum of $7,500 (Tarion):
- Living expenses: a fixed $150 a day for meals and accommodation, from the missed date until the new closing date. You do not need receipts.
- Other costs caused by the delay: for example extra moving or storage. You do need receipts for these.
- Short notice: if the builder gives you less than 10 days notice of the delay, you get $1,500 ($150 x 10 days).
When you can walk away
If the home is not finished by the Outside Closing Date, you have a 30-day window to terminate the agreement. If you do, you get a full refund of everything you paid, including deposits, extras and upgrades, plus interest, and you can still claim delayed closing compensation (Tarion).
Tarion also protects your deposit up to set limits (see our deposit guide).
Delays that do not pay compensation
Two situations let a builder move dates without paying you:
- Unavoidable delay: an extraordinary event outside anyone's control, such as a strike, fire, pandemic or act of war. The builder can extend the dates by the length of the delay, with written notice.
- Mutual agreement: signing an amendment that changes a date can mean giving up compensation. Ask your lawyer first.
How to make a claim
Send your claim to the builder within 180 days of closing, or of the date you terminated the agreement. Include receipts for direct costs. If the builder does not pay, you can claim through Tarion's MyHome portal during your first year of possession, or up to 365 days after you terminated (Tarion).
What to check before you sign
Before you sign, read the Statement of Critical Dates, not just the move-in season in the brochure. At Collection on 27 in Kleinburg, occupancy is scheduled for fall 2028. At UpTown Woodbridge, Fieldgate has not confirmed closing dates yet. Plan your lease or sale around the latest possible date.
We read the dates and the addendum with you before you sign and work for you on price, lot, layout, incentives and upgrades. The builder is there to maximize their profit. We are here to maximize your dream. Explore your options with us.
Questions buyers ask
How much compensation do I get if my new home closing is delayed in Ontario?
On a new freehold home, up to $7,500 once the Firm Closing Date is missed: $150 a day for living expenses with no receipts, plus other costs like moving and storage with receipts.
Can a builder delay closing without paying anything?
Yes. A tentative closing date can be extended twice by up to 120 days each with 90 days notice, and unavoidable delays like a strike or fire pay nothing.
Can I cancel if my new home is delayed too long?
Yes. If the home is not complete by the Outside Closing Date, you have 30 days to terminate and get all deposits, extras and upgrades back with interest.
How do I claim delayed closing compensation?
Claim from the builder within 180 days of closing. If it does not pay, claim through Tarion MyHome within your first year of possession.
*Prices are as published by each builder, many net of the HST enhanced rebate where the buyer qualifies, and can change without notice. E.&O.E.